- Joined
- Nov 12, 2012
- Posts
- 28,031
- Qantas
- Platinum
- Virgin
- Platinum
- Star Alliance
- Silver
Could all costings etc please have a separate line for, or exclude, taxpayer subsidies in the capital cost, RECs,tariffs etc and then analyse 'break even' point.
Off the cuff pricing for a battery / grid interactive controller here is about $8000. This may include slightly higher installation costs to mitigate the "rural 480" grid connection as installed in WA and batteries are extra.
Can we have more examples of existing installations?
Just wandering
Fred
AFF Supporters can remove this and all advertisements
Could all costings etc please have a separate line for, or exclude, taxpayer subsidies in the capital cost, RECs,tariffs etc and then analyse 'break even' point.
.The Finkel report implies that Australia’s grid is no longer fit for purpose, saying it is antiquated and does not have the policies and market design that would encourage the technology solutions that already exist for high levels of wind and solar
.The Germans have spent billions of Euro upgrading their grid for renewables.We have basically spent zilch.It should have been done in SA before increasing the renewable input.
Also in your link there is no mention of other serious blackout episodes such as November 2015 in South Australia when there was no storm activity because there was no wind.The Hazelwood connector kept working.If it wasn't for the Augusta coal fired power station still operating you may very well have had a state wide blackout then.
The point is the Interconnector "failed"on both occasions because it was doing what it had to when faced with a very large drop in power output from South Australian power generation and that large fall on both occasions was from wind generation.
The predicted weather front moved through SA on the afternoon of Wednesday 28 September 2016, including high winds, thunderstorms, lightning strikes, hail, and heavy rainfall.
The weather resulted in multiple transmission system faults. In the short time between 16:16 and 16:18, system faults included the loss of three major 275 kV transmission lines north of Adelaide.
Generation initially rode through the faults, but at 16:18, following an extensive number of faults in a short period, 315 MW of wind generation disconnected (one group at 16:18:09, a second group at 16:18:15), also affecting the region north of Adelaide.
The uncontrolled reduction in generation resulted in increased flow on the main Victorian interconnector (Heywood) to make up the deficit.
This resulted in the Heywood Interconnector overloading. To avoid damage to the interconnector, the automatic-protection mechanism activated, tripping the interconnector. In this event, this resulted in the remaining customer load and electricity generation in SA being lost (referred to as a Black System).
You cant have it both ways RAM.
That wind power wasn't responsible for the September blackout because wind power shut down because of incorrect settings in response to the grid problems.
But the Interconnector was responsible in November because of incorrect settings.
Both events were precede by drops in the production of power by wind generators.
Unfortunately a HV line (ie connector) from WA to SA is considering "un-economic".
Wind (at least so far) has been found to be reliable in WA. Enough so that the state owned generators have used it in place of upgrading distribution lines.
Is there data available on the efficiency of the existing wind farms? Rating versus actual daily generation (and highlighting the amount of time with no generation).
Just wandering
Fred
Mr Murray said the only survey done to gauge locals' opinion had suggested that 92 per cent of them supported the plan.
"The two wind turbines would save us consuming something like 167,000 litres of diesel per year," he said.
"Surely if you were talking about visual impact on a World Heritage site, you would have to wonder why the two wind turbines would be struck down," he said.
"Whereas the Abbot Point coal loading facility in the Great Barrier Reef World Heritage [area] would be approved?
"We'd have to ask where is the consistency?"
As a World Heritage-listed site, it had to be approved by Federal Environment Minister Josh Frydenberg.
But he has rejected the proposal, which he said would "have clearly unacceptable impacts".
A spokesman for Mr Fydenberg said the "Government considered the proposed wind turbines would create a considerable, intrusive visual impact".
South Australia has announced Elon Musk's Tesla as the principal builder of the world's largest lithium ion battery to expand the state's renewable energy supply.
The mega-project will be built in conjunction with French renewable energy firm Neoen and paired with Neoen's existing Hornsdale Wind Farm near Jamestown, north of Adelaide.
SA Premier Jay Weatherill said the "extraordinary collaboration" would deliver a grid-scale battery that would "stabilise the South Australian network as well as putting downward pressure on prices".
SA Government annouces that Tesla will make the world's largest biggest battery to supplement their electricity grid.
South Australia announces Tesla as backer of world's largest battery
At a press conference in Adelaide, the South Australian Premier’s office warned journalists not to ask Mr Musk any questions relating to issues other than energy, saying special guests “may leave the stage”.
After making media wait for 90 minutes for the event, reporters were allowed to ask questions in a question-and-answer format tightly-controlled by Mr Weatherill.
Mr Musk has had a rough week as the head of Tesla. The company’s shares have dropped almost 20 per cent since late June, and late last week it announced it would not be able to produce as many electric cars as anticipated due to a battery production shortages.